Calculating a Plan
Once all planning data has been entered, the plan can be calculated.
This is done from the Calculate section in the Planning Module.
Here you determine:
-
Which data is included in the calculation.
-
The reporting period to be calculated.
-
Where the calculated results are stored.
Calculate Screen Layout
The Calculate screen consists of two sections:
-
Left side: Calculation settings.
-
Right side: Data selection, such as scenarios and Cost Centers.
This also allows you to calculate only part of a plan, for example when performing scenario analysis.
Explanation of the Fields
The numbered items on the screen have the following functions.
1. Start and End Year
Select the planning period.
For example:
-
2025 to 2025 - Single-year plan.
-
2024 to 2027 - Multi-year plan.
2. Actuals Through Period
Select the month up to which Actuals are used.
For example:
-
Through April - Actuals are used for January through April.
-
From May onward - Planning data is used.
3. Save to Dossier
The calculated plan is saved to the selected dossier.